What is the deadline for filing a Claim of Lien after the completion of work?

Prepare for the Georgia Master Plumbing Exam. Utilize flashcards and multiple-choice questions, each with hints and detailed explanations. Ace your licensing exam!

The correct answer is three months. In Georgia, a contractor or subcontractor must file a claim of lien within three months of the completion of their work on a project. This deadline is critical because it establishes the timeframe in which the party must assert their right to a lien against the property for unpaid work.

Filing within this period ensures that the claim is legally valid and enforceable, providing the party with a means to seek compensation. If a claim is filed after three months, it may be considered untimely and could jeopardize the ability to collect payment through lien enforcement.

This timeframe is outlined in the Georgia lien law, which aims to protect the rights of those who provide labor and materials for property improvement. Understanding this timing is essential for contractors and those in the plumbing industry to safeguard their financial interests effectively.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy