What is the time frame within which a claimant must commence action for the recovery of a claim to prevent a lien from becoming invalid?

Prepare for the Georgia Master Plumbing Exam. Utilize flashcards and multiple-choice questions, each with hints and detailed explanations. Ace your licensing exam!

The correct answer is 12 months because it aligns with the statute of limitations for filing a lawsuit regarding the recovery of a claim in the context of construction liens. In Georgia, once a lien has been placed on a property for unpaid services or materials, the claimant has a period of 12 months to initiate legal action to enforce that lien. If the claimant fails to commence action within this time frame, the lien becomes invalid, meaning the claimant loses the ability to leverage that lien for recovery. Understanding this time frame is essential for anyone involved in the construction industry or providing services that can lead to a lien, as it emphasizes the importance of timely legal action to secure payment.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy